class="single single-post postid-182550 single-format-standard custom-background group-blog masthead-fixed full-width singular wpb-js-composer js-comp-ver-4.12 vc_responsive"
Gov. Ricketts, Roads Department Announce Major Roads Construction Projects | KTIC Radio

Gov. Ricketts, Roads Department Announce Major Roads Construction Projects

Gov. Ricketts, Roads Department Announce Major Roads Construction Projects
Courtesy Governor's Office

LINCOLN – Today, Governor Pete Ricketts and the Nebraska Department of Roads (NDOR) announced $300 million in new transportation projects that will be constructed and funded by the Build Nebraska Act (BNA) and the Transportation Innovation Act (TIA).  In addition to the eight projects funded for construction by this investment, NDOR will begin design work on an additional 12 projects and plan for two others.

“This announcement follows a historic commitment from the State of Nebraska to build the 21st-century infrastructure we need to grow our state,” said Governor Ricketts.  “Thanks to Senator Fischer’s Build Nebraska Act and the Transportation Innovation Act, which my administration collaborated on with the Legislature, we are working toward fulfilling Governor Orr’s vision for expanding our state’s expressway system.  I appreciate the work of the many legislators, community leaders, and other stakeholders who have supported improvements to our transportation system over many years. ”

Today’s announcement comes after several months of work where NDOR engaged with more than 2,000 stakeholders as the agency updated and expanded its project prioritization process and identified priorities for transportation projects in Nebraska.  The projects announced today have been selected based on a process that more fully considers economic impact and stakeholder input, while continuing to consider engineering performance.  In addition to the updated project prioritization process, NDOR also considered a variety of other factors when selecting projects, including:  geographic inclusion, corridor completion, previous investment on a corridor, and progress on the Expressway System or High Priority Corridors.

“This round of Build Nebraska Act and Transportation Innovation Act projects will help deliver great transportation improvements and expand our expressway system across our state,” NDOR Director Kyle Schneweis said. “We know these projects will have a positive impact on our communities and help to grow our economy.  We also know Nebraskans support these projects because of our first-ever public input process during which we talked extensively with and listened carefully to taxpayers across the state.”

The construction projects announced today represent only a portion of the funds the state has available for capital improvement projects.  As the state grows, NDOR will continue to program additional funds in future years to address new transportation priorities and opportunities.

All eight projects slated for construction are projected to begin by 2024, with the exception of US-275 from Scribner to West Point, which will be the state’s first design-build project.  The design-build process was authorized in the TIA, and it will allow work to begin years earlier.

TIA Priorities

A full list of projects slated for construction, design, and planning is included here:

Projects selected for Construction

Project Name Project Length (miles) Project Cost (millions)
I-680 from Fort St to Irvington in Omaha, 6 lane interstate 1 $29
N-7 from Bassett to Springview, 2 lane highway modernization 2 $2
US 6 at 192nd St and West Dodge Road in Omaha, Interchange improvements 1 $17
US 26 from Minatare to US 385, 4 lane divided highway 18 $60
US 75 at Chandler Road North (northbound) in Omaha, Add lane to northbound lanes 3 $10
US 77 / Fremont Southeast Beltway, 4 lane divided expressway 4 $26
US 83 from McCook to North Platte, Super 2 60 $60
US 275 from Scribner to West Point, 4 lane divided expressway with a bypass around Scribner 25 $90

 

Projects selected for Design Work

Project Name Project Length (miles)
I-80 Newberry Interchange improvements and L56G from Platte River to US 30 in North Platte, 4 lane divided highway 2
N-50 from Louisville to Springfield, 4 lane divided highway 9
N-92/US 275 East of Yutan, 4 lane divided highway 10
N-370 from Gretna East to I-80, 6 lane divided highway 4
N-370 from I-80 to Bellevue, 6 lane divided highway 12
US 30 Grand Island East Bypass, 4 lane divided highway 6
US 30 from Kearney to Grand Island, Super 2 36
US 75 from Nebraska City to Murray, 4 lane divided expressway 17
US 77 Wahoo to Fremont, 4 lane divided expressway 16
US 81 from York North, 4 lane divided expressway 43
US 275 from West Point to Pilger, 4 lane divided expressway with bypass 29-30
US 385 from Alliance to Chadron, Super 2 59

 

Projects selected for Planning Work

I-80 Interchange(s) in Omaha/Sarpy County, New interchange(s) construction
Lincoln East Beltway , 4 lane divided highway

 

More information on the projects announced today is available at http://roads.nebraska.gov/projects/grow-ne/cap-improve/selection.